Simferopol TPP output to full capacity

Tavrichyeskaya CES (Simferopol) Thursday starting with the second block was introduced into a nominal power, RIA Novosti reported the press service Rostec.

Симферопольская ТЭС выведена на полную мощность

Currently, a plurality of blocks is supplied to the power grid 480 MW.

Besides, on Thursday night began to supply electric power to the second block of TPP Balaklava (Sevastopol). Its output is the nominal capacity is planned in the coming days.

As noted Rostec, that stations have already begun to receive payments, but without component on ROI. That is, the payment is at cost, covering gas costs and other operating expenses.

The first power stations Crimean began work this autumn. As previously reported by Deputy Energy Minister Andrei Tcherezov, commissioning of the second stage of both TPP is planned before the end of 2018 , subject to the availability of electric grid infrastructure and gas networks.

Construction of the Crimean TPP is a member of the company Rostec "Tekhnopromexport". During the construction used 4 Gas turbine Siemens, which were purchased 2015 year for the power plant in Taman. However, later it became known, that they sent to the Crimea.

Siemens is trying to gain recognition in the Russian court deal to turbines invalid because, that the products recovered in the region, are under sanctions of the European Union. However, the court took the side of "Tekhnopromexport", rejected the claim of the German company.

                          